Milton's 13 precincts voted 9,727 to 7,717 against renewing Fulton County's 0.75% transportation sales tax on Nov. 3, a 55.8% no vote. Milton Journal reported those unofficial results on Nov. 4. Across Fulton County outside Atlanta, the renewal passed 129,283 to 125,417, or 50.8%. Milton's 2,010-vote no margin was smaller than the 3,866-vote yes margin countywide. The tax now continues from April 1, 2027, through March 31, 2032, and Milton's estimated share is $44,178,196.

For people who drive Bethany Road, Hopewell Road or the Deerfield side of town every day, the result matters less than how the list is built. Milton named only two projects in its plan for that money. Everything else is a dollar figure attached to a category, and the specific roads, bridges and paths will be chosen later by City Council, one agenda item at a time.

Milton's share was set by population before anyone voted

Milton's local result had no effect on its allocation. Fulton County's 2026 TSPLOST agreement gives each of the 14 participating cities a share based on 2024 Census population estimates for Fulton outside Atlanta. Milton's 41,490 residents make up 6.77% of that total, Milton Journal's explainer reports. The county's Aug. 4 announcement put the program at about $650 million across all 14 cities from 2027 to 2032.

At the forecast level, Milton's neighbors receive these amounts:

City Forecast-level TSPLOST amount, 2027–2032
Roswell $98,202,519
Johns Creek $86,425,926
Alpharetta $71,633,843
Milton $44,178,196

The 0.75% tax is collected on sales across the county and divided by population. Milton's precincts had no say in the split. The only real choice left is how the city spends its share.

Two projects have names. Everything else is a category.

Milton's project list, which the county published as a Milton fact sheet, names only two projects:

  • SE Crabapple: new roadwork in southeast Crabapple connected to the District at Mayfield.
  • The Deerfield Connector: a new street linking State Route 9 with Deerfield Parkway.

Both sit under "operations and safety," along with general corridor and roundabout improvements. The rest of the list names no specific bridge, sidewalk, trail segment or road for resurfacing. When staff presented the draft in May, the City described the list as giving the City and the Council discretion over specific tasks. Milton's May 18 agenda report says the broad categories leave specific tasks open on purpose so that later planning, engineering, market conditions and Council priorities can shape them.

Mayor Peyton Jamison said so plainly when the list came before Council, according to the City of Milton's recap:

"This is the very … beginning, and we'll get into the actual projects and weeds down the road."

The tiers show which money depends on sales

The $44.2 million figure assumes collections hit forecast, and sales tax revenue is never guaranteed. The county's 2026 TSPLOST agreement sets three funding levels. Tier 1 reflects 85% of forecast revenue, Tier 2 brings the total to 100%, and Tier 3 applies only if collections reach 115%. Tier 1 projects are funded first. Tier 2 and Tier 3 go ahead only if the money arrives.

Purpose Tier 1 (85% of forecast) Added in Tier 2 (100%) Added in Tier 3 (115%)
Maintenance and safety improvements $10,000,000 none none
Bridges $10,000,000 none none
Operations and safety, incl. SE Crabapple and Deerfield Connector $11,000,000 $4,000,000 $4,000,000
Pedestrian, bicycle and streetscape $4,000,000 $2,626,729 $2,626,730
Quick response $1,551,467 none none
Project management $1,000,000 none none
Running total $37,551,467 $44,178,196 $50,804,926

The structure shows which work is first in line. Bridges and road maintenance get their full allocations in Tier 1, at $10 million each. Only two lines grow if collections run strong: operations and safety, and walking, biking and streetscape. If sales tax revenue falls short of forecast, those two lines shrink first. Milton Journal's widely shared figures of $15 million for operations and $6.6 million for pedestrian work combine Tiers 1 and 2. At the Tier 1 level, which is funded first but still depends on collections, those numbers are $11 million and $4 million.

Fields Crossroads shows how long a TSPLOST promise takes

The Bethany Road–Providence Road intersection at Fields Crossroads, currently an all-way stop, shows how long the gap between a vote and a finished project can be. Voters approved the intersection improvement in November 2016 as part of the first TSPLOST referendum. It appears as a Tier II project on Milton's 2017–2022 list. The City's public project page on ClearGov projected $2.2 million in spending, a figure last updated in August 2021.

On Oct. 19, 2026, almost ten years after that vote, City Council authorized condemnation of the last piece of property needed to build a roundabout there. The City's meeting recap said negotiations with that owner had been going on for about two years. The vote lets bidding begin while those talks continue.

A project with a name and a budget from 2016 is only now reaching bidding. The 2027–2032 list has two named projects and about $33 million in Tier 1 categories with no specific locations attached, so most of what the new money builds will be chosen, engineered and approved over the coming years.

What the earlier rounds already changed

Residents can already see what this tax has paid for. Milton's TSPLOST page lists three Hopewell Road intersections as completed Tier I projects from the 2017–2022 program: Hopewell at Bethany Bend/Bethany Way, Hopewell at Thompson Road/South Thompson Road, and Hopewell at Hamby Road. The Morris Road widening is on that same Tier I list. In a July 2026 update, the City described the widening, sidewalks and multi-use path between the Deerfield Avenue/Webb Road roundabout and McGinnis Ferry Road as ongoing TSPLOST-funded work. In 2025, the City also called the Birmingham Road middle-bridge replacement a TSPLOST-funded project.

Not every recent road project is TSPLOST work. The Freemanville Road bridge over Cooper Sandy Creek reopened to two-way traffic on Friday, Oct. 23, after a five-month closure, and crews are still finishing work at the site. The City lists that replacement as a GDOT/State project. It doesn't count against the new $10 million bridge allocation, which leaves that money for other bridges in Milton.

Where the next road decisions get made

Choosing Milton's next projects will look like what happened at Council in the past few weeks. On Nov. 2, Council discussed traffic-calming options for Hopewell Road. Members favored the larger concept, with four wider landscaped medians, resurfacing and restriping, and a pedestrian crossing with a flashing beacon, but took no project action. Appen Media reported that option at $200,000, compared with $125,000 for a smaller stamped-concrete-median version. At the Oct. 19 meeting, Council also approved final engineering by Moffatt & Nichol to realign Mid Broadwell Road's connection to Mayfield Road within the District at Mayfield, the same area as the named SE Crabapple project.

Specific projects under the new tax will come up the same way, as engineering contracts, right-of-way approvals and design options on regular Council agendas. Council adopted its 2027 meeting and work-session calendar on Nov. 2, so those dates are already set. The vote totals cited here stay unofficial until Fulton County certifies them, and the Georgia Secretary of State's results site has the current count. Collections under the renewed tax begin April 1, 2027.

A roundabout, connector street or bridge replacement can change how a property is reached, how it's seen from the road and how a buyer reads its location. If you own land or a home near Fields Crossroads, southeast Crabapple or the Deerfield corridor, Andrea Seeney can walk you through what is planned nearby and how it may affect the way your property is presented. Request a Confidential Consultation.

WORK WITH ANDREA

Whether you are buying or selling, Andrea puts her clients' interests before her own in every transaction. She scours her local network to find the most exclusive properties, and she secures the best deals. Andrea maximizes each property's market value with her streamlined process and unmatched marketing strategy.

Follow Me on Instagram